Documented ProcedureBPA
D o c u m e n t e d P r o c e d u r e
MPZ 001
4100-001-06.05
Department TB / Schell
Assembly Plan
Toothed Racks
Servo Line
Page 15 24
Rev. Index D Name 01.06.05 Schell
Date 3.05.2011 released 01.06.05 Lorch
MPZ_001_engl.doc
The following is a mounting example on the machine bed
Steps 4 to 10 are the same as with the mounting instruction without
supporting surface.
Pinning
3. Tighten the hexagon socket screws
of the second rack in such a way that
adjustment is still possible. Then
remove the companion piece.
Clamp the rack with screw
clamps at all pinholes as shown
on the picture opposite.
Drill the pinholes into the machine
bed according to the holes
provided in the rack.
Ream the drilled holes together to
the tolerance fit H7 for the
straight pins.